Welcome To our New Indoor Heated Pool Album..We only Started work at the end of October look at how far we have already are..Trees took 1 day to remove ready for the digger this was another 3 to 4 days work...Pool setup took 1 week then Poured on Thursday the 10th November..Bricks took 3 days to get this far..


Taking Trees out Ready for work

Digging Footings Pouring Footings

Boom Pump

Ready For Set up Plumbing Done


Set Up Ready For Concrete


Big Job But Azura Pool Guys have it Sorted

Brick work Started Pool Poured Looks Great

Ready to Pour Monday the 28th November Ready for the rest of the building now
Well its taken 1 month to get this far with progress with things going this well we are on track for the Grand opening in early 2012..Keep Posted for the Grand Opening Date..Many Thanks for all the hard work and effort put in by all who have helped get this far..
After Everyone had there Christmas Break and All of our guests left we started the hard work again on Saturday the 4th February As you can see we are coming along.

|